| S.No. | Name of Hydel Project | Department/Company | Location | Current Status |
|---|---|---|---|---|
| 1 | Kurhed (4.5 MW) | Himachal Hydro | HP | Commissioned |
| 2 | Tulang (3 MW) | Himachal Hydro | HP | Commissioned since July 2014 |
| 3 | Kalheh (2.5 MW) | VKG | HP | At NOCs stage |
| 4 | Shat (5 MW) | SKB | HP | NOCs obtained, forest clearance in final stage |
| 5 | Chharor (3 MW) | SKB | HP | NOCs obtained, forest clearance in final stage |
| 6 | Kurpan (4.8 MW) | Himprabha | HP | All NOCs obtained, ready for construction |
| 7 | Kuril (5 MW) | Sahu HPPL | HP | Survey, hydraulic studies, cost analysis, structural designs, and tender documentation complete. Ready for construction. |
| 8 | Kurtha (5 MW) | Sahu HPPL | HP | Commissioned since October 2014 |
| 9 | Chonned (15 MW) | Parvat HPPL | HP | Survey and investigation complete, all NOCs obtained |
| 10 | SJVNL (412 MW) | SJVNL | HP | Consultancy for structural design and fabrication drawings for rope drum hoist and portal gate for Rampur hydel project. Commissioned. |
| 11 | Swad (5 MW) | Micro Hydro Pvt. Ltd. | HP | Due diligence at construction stage |
| 12 | Surah (1.5 MW) | Micro Hydro Pvt. Ltd. | HP | Due diligence at construction stage |
| 13 | Neri (5 MW) | M/S Archit Butel | HP | Tenders, structural design, and structures for civil/hydro-mechanical equipment prepared. Ready for construction. |
| 14 | Kurpan Bagipul (1 MW) | Micro Hydro Pvt. Ltd. | HP | Revised DPR prepared and submitted for TEC |
| 15 | Baleni Ka Nallah (2 MW) | Manimahesh Urja | HP | DPR prepared and submitted for TEC |
| 16 | Panchpula (0.5 MW) | ERS | HP | DPR prepared and submitted for TEC |
| 17 | Shikari Mata (0.3 MW) | Shepmandi | HP | DPR prepared and submitted for TEC |
| 18 | Dev Kalakameshwar (0.15 MW) | Shepmandi | HP | DPR prepared and submitted for TEC |
| 19 | Panjoud (0.5 MW) | Shepmandi | HP | DPR prepared and submitted for TEC |
| 20 | Kanda (400 KW) | M/S Bhagwati Power Projects | HP | DPR prepared and submitted for TEC |
| 21 | Bharog (0.250 MW) | M/S Ramu Ram | HP | DPR prepared and submitted for TEC |
| 22 | Megal (0.08 MW) | M/S Ramu Ram | HP | DPR prepared and submitted for TEC |
| 23 | 30 Small Hydel Projects (120 KW to 10 MW) | Kargil Renewable Energy Development Agency (KREDA) | J&K | Planning and survey for 30 projects in Zanskar River (3500m-4500m elevation). 30 PFRs submitted to KREDA and MNRE. 13 projects approved by IIT Roorkee, DPRs prepared. |
| 24 | Nogli (3.0 MW) | Kamaksha Electrical Power Project Pvt. Ltd. | HP | DPR prepared, TEC obtained, structural designs completed. Under construction. |
| 25 | Nazonga (0.9 MW) | Dev Bhumi Hydro Power Project Pvt. Ltd. | HP | DPR prepared, TEC obtained, structural designs completed. Under construction. |